Projects
MSH LLP has successfully implemented a number of projects in the oil and gas industry and civil construction.
We have been involved in design, equipment supply, installation, and commissioning at key facilities of oil and gas production companies.
Our experience includes working in challenging climatic conditions and cooperating with leading enterprises in the industry.
The main result of our projects is reliable and safe solutions that help Customers achieve their goals on time and with high quality.
Production Base
Production Base
Located in the industrial zone of the city, SU-4.
Total area of the production base: 1.5247 hectares.
– welding workshop
– parking area for special-purpose vehicles
– painting station
– repair bays
– car wash
– storage area
– crane operation area
– office and welfare facilities
Shift Camp
At the North Buzachi field, there is a shift camp for rotational personnel accommodation with a capacity of 400 beds, covering an area of 1.2 hectares, as well as a repair base for special equipment and machinery with an area of 0.5 hectares.
North Buzachi Field
Experience and completed works:
  • Construction, installation, and welding works for oilfield development.
  • Electrical installation works, including installation of instrumentation and automation equipment (I&C).
  • More than 60 km of 20 kV power transmission lines commissioned.
  • Power supply and lighting provided to more than 400 wells.
  • Approximately 200 transformers and 20 km of overhead power and cable lines installed.
  • More than 700 km of oil product pipelines laid, with over 400 wells connected.
  • Experience in pipeline laying and repair under difficult conditions (marshy and saline areas) — more than 400 km.
  • More than 50 manifolds installed.
  • Construction and arrangement of 20 kV power transmission lines.
The Company also carried out works at the North Buzachi field involving the assembly and installation of pumping units such as:
Zaman SKD-8, PSHGT 8-3-5500-05, Lufkin C4556D-305-168, C320D0-256-144, C320D-213-120.
Foundation preparation for pumping units.
Pre-start preparation, adjustment, and commissioning of pumping units.

Installation and commissioning of control stations.

KarakudukMunai JSC
• Design and construction of a laundry complex and expansion of the canteen at the field.
• Construction and reconstruction of access roads at the field with a total length of 21 km, including tunnels under the roads.
• Construction of 6 kV high-voltage power lines.
• Performance of construction and installation works.
• Replacement of cable lines at the Karakuduk field.
• Construction and installation works for the project “Reconstruction of electrical networks at the Karakuduk field”.
Maersk Oil Kazakhstan GmbH – Dunga Field
  • Design works for field reconstruction.
  • Construction and installation works.
  • Welding and installation works.
  • Electrical installation works.
  • Installation of instrumentation and automation systems (I&C).
Karazhanbas Field
At the Karazhanbas field, the following were installed: a 110/6 kV power transformer, 110 kV current transformers (CT), 110 kV voltage transformers (VT), 110 kV station service transformers (SST), and auxiliary equipment for the second transformer, installation of capacitor banks, as well as implementation of an automated commercial electricity metering system (ASKUE) and SCADA.
KOMMUNAI Company
Komsomolskoye Oil Field
Civil construction
MunaiService-Holding LLP actively develops the civil construction sector, implementing large-scale and regionally significant projects. Each facility delivered by the Company is distinguished by thoughtful architecture, high quality of execution, and close attention to detail.
One of the landmark projects is the Zodiac Business Center, located in the very heart of the city, in the 17th microdistrict. This modern business complex combines style, functionality, and comfort. Zodiac has become not just a workplace, but a symbol of progress and reliability, reflecting the Company’s professional approach to construction.
Another notable project is Ivushka — cozy townhouses by the sea, created for comfortable and relaxed living. This residential complex combines the tranquility of the coastal area with the advantages of urban infrastructure, offering a modern lifestyle in harmony with nature.
In 2021–2022, MunaiService-Holding LLP carried out construction works for SML SEMBOL Construction — Phase II of the multifunctional hotel and tourism complex located in the “Warm Beach” area of Aktau, Mangystau Region, including the “Golf Hotel with Villas” and the “Town Center”.
A special place among the implemented projects is occupied by the construction of a recreation base and cottage complex for Zhana Kazba company (2022–2025). As part of the project, administrative and hotel facilities as well as cottage-type buildings are being constructed — a total of 238 modern townhouses. This large-scale project has become another confirmation of MunaiService-Holding’s competence in delivering turnkey projects, from design to commissioning.
MunaiService-Holding LLP is proud of its contribution to the development of urban and tourist infrastructure in Western Kazakhstan, creating spaces where quality, comfort, and reliability become a standard of living.

IVUSHKA Family Resort

Turnkey construction works in the apartment resort complex “IVUSHKA FAMILY RESORT”.

Townhouses.

General Contractor: MunaiService-Holding LLP.

News
Latest news and events related to the Company, including completed projects and plans for the future.
Please expect new updates as construction is completed; additional information will be provided.
More details
Please expect new updates as construction is completed; additional information will be provided.
More details
Please expect new updates as construction is completed; additional information will be provided.
More details
Please expect new updates as construction is completed; additional information will be provided.
More details
Gallery
A gallery of images showcasing projects and facilities implemented by the Company.
Contacts
Phone numbers:
8 (7292) 20 14 54
+7 777 911 1111
+7 701 522 98 55
+7 771 771 88 44
Email:
too.msh2010@mail.ru
hr_munaiserviceholding@mail.ru
Address:
Mangystau Region, Aktau city, 17th microdistrict, Zodiac Business Center
Made on
Tilda